Latest News

This page is intended to keep you up to date with the proposal as developments occur.

August 2011
Energiekontor UK has completed the project financing of Hyndburn wind farm. This is a significant milestone for the UK company and will allow construction of its third UK wind farm to proceed. The wind farm, scheduled to be fully commissioned in autumn 2012, will use REpower mm82 turbines to provide an installed capacity of 24.6MW. Galliford Try Infrastructure has been awarded the balance of plant contract to build the wind farm and are expecting to commence construction works late 2011. Dinsdale Moorland Services are appointed to undertake moor restoration works which are part of a long term ecological enhancement plan to improve the peat moorland.

December 2009

The planning application for the proposed Hyndburn Wind Farm was submitted to Hyndburn Borough Council on 9th December 2009 and was confirmed as being valid on 10th December 2009. Additional copies of the full planning application have been provided to Hyndburn Borough Council in order that they may be displayed at the following venues for the public to review the wind farm proposals:

Hyndburn Borough Council, Scaitcliffe House, Ormerod Street, Accrington - 09.00 to 17.00 hours Monday to Friday

Oswaldtwistle Public Library, Union Road, Oswaldtwistle - Monday 10.00 to 19.00 hours, Tuesday, Thursday and Friday 10.00 to 17.00 (Closed lunchtime 12.00 to 13.00 hours and all day Wednesday), Saturday 10.00 to 12.30 hours

Accrington Town Hall, Blackburn Road, Accrington - Monday to Friday 09.00 to 16.00 hours, Saturday 09.30 to 15.30 hours.

The wind farm development could contribute a substantial amount of clean and sustainable electricity to help meet our needs in the face of increasingly significant environmental challenges. In response to our Community Update leaflet we were very pleased that the majority of replies were in favour of the wind farm. We would encourage anyone who wants to demonstrate their support for the planning application to make their views known to the Council. For your convenience there is a letter generating facility on this website - just click on the ‘Support our Proposal’ link on the left and complete your details.

The Non-Technical Summary of the Environmental Statement can be downloaded by clicking here.

July 2009
A planning application was submitted on 22nd July 2009 to Hyndburn Borough Council for the erection of an up to 60m high meteorological mast for a period of up to 36 months on land on Oswaldtwistle Moor. Site Location plan - download. The meteorological mast will allow a more detailed wind resource assessment of Oswaldtwistle Moor.

April 2009
Information Leaflet Download...

May 2007
Consultation Leaflet Download...

Public Exhibitions were held at Oswaldtwistle and Church Cricket Club on 11th May 2009 and at Accrington Town Hall on 13th May 2009 between 2pm and 8pm. If you were unable to attend, the boards that were displayed can now be found on the Public Engagement area of this web site.”

IMAGE OF TYPICAL WINDFARM